Get in Touch
Home / Go Solar
Get started

Schedule a FREE consultation with us today!

Tell us about your roof and your bills, and we will come and look at it.

Please fill the form and we will get in touch with you for the consultation.

Commercial Solar Panel Subsidy in UP
Residential Solar Panel Subsidy in UP
Commercial and Industrial Solar Solutions 
Solar Panel Subsidy in UP
Our addressGround Floor Hall, Plot No. 4, Vrindavan Yojana, Sector 10A, Lucknow, Uttar Pradesh 226029
Contact detailsM:+91 93166 75306, +91 63593 33222

Book your free consultation

Pick what fits you and we will call you back.

PM Surya Ghar

What the subsidy is actually worth

Central Financial Assistance is fixed by the size of the system, not by what you spend on it. These are the current residential rates under PM Surya Ghar: Muft Bijli Yojana.

1 kWRs 30,000The first kilowatt is subsidised at the full rate.
2 kWRs 60,000Rs 30,000 for each of the first two kilowatts.
3 kW and aboveRs 78,000The third kilowatt adds Rs 18,000. Beyond 3 kW the subsidy stops rising, even on a 5 kW or 10 kW system.
Housing societies are treated differently. Common-area load — lifts, pumps, corridor and compound lighting — draws Rs 18,000 per kW, up to 500 kW for the society as a whole. That is claimed by the society, not by individual flats.

Figures are the central scheme rates. Uttar Pradesh has run its own top-up alongside them, and state and DISCOM incentives change from time to time. We confirm what is actually live on the day we survey your roof, rather than quoting you a number that has moved on.

The process

From first call to subsidy in your account

01

Site survey

We come out, measure the usable roof, check your sanctioned load and read your last few bills. No charge, and no obligation.

About 40 minutes
02

Design and quote

We size the system against your actual consumption rather than your roof area, and show you the cost before and after subsidy.

2 to 3 days
03

Portal registration

We register the application on the national portal and file for feasibility approval with your distribution company — MVVNL for most of Lucknow.

7 to 30 days
04

Installation

Our own crews install it. Panels and inverter are ALMM-listed, which is a condition of the subsidy, not a preference.

1 to 3 days on site
05

Net metering

Inspection, then the bidirectional meter goes in. Whatever you export beyond what you draw is credited against your bill.

7 to 15 days
06

Subsidy credited

The CFA is paid directly into the bank account on the application. Start to finish is usually 30 to 90 days, depending on how quickly the DISCOM moves.

Direct transfer
Before you apply

What to keep ready

None of this is difficult to find. Having it to hand on survey day is the difference between an application filed that week and one filed a fortnight later.

  • A recent electricity bill — we need the consumer number and your sanctioned load
  • Aadhaar or photo ID of whoever the connection is in the name of
  • Proof of ownership of the property, or a no-objection letter from the society
  • Bank account details, since the subsidy is transferred directly
  • A photograph of the roof, if you happen to have one
Common questions

Things people ask us first

Will a bigger system get me a bigger subsidy?

No. The Central Financial Assistance is capped at Rs 78,000 for a residential connection. A 5 kW or 10 kW system is often the right call for a large household, but the subsidy on it is the same as on 3 kW.

Can I claim it on a connection that has already had solar?

No. The subsidy is once per connection. If a previous owner claimed it on the same meter, that connection has used its entitlement.

Do I have to use a registered installer?

Yes. The subsidy is only released for installations by a vendor registered on the national portal, using ALMM-listed panels and inverters. Fourcell is registered, and we install with our own crews rather than subcontracting.

How long before the money reaches me?

Typically 30 to 90 days from application to credit, and most of that is waiting on the distribution company for feasibility approval and the meter inspection. The installation itself is a day or two.

What happens to the power I do not use?

It goes back to the grid under net metering and is credited against what you draw at night. Uttar Pradesh settles the balance annually, so a summer surplus offsets a winter shortfall.

Do you work outside Lucknow?

Yes. Lucknow is our north India base, but we deliver across Uttar Pradesh and several other states from Surat. Tell us the city on the form and we will say honestly whether we can serve it well.